Too much on at once? A simple capacity check for small teams

Count overlapping work per person per period, and fix the pile-ups before they land.

Small teams rarely fail because the work is too hard. They fail because too much of it lands on the same people in the same weeks. Each project looks fine on its own; the trouble only shows when you line them up and notice that one person owns four of them in March.

You don't need resource-planning software or timesheets to catch this. A rough capacity check, using the names and dates you already have, will find most pile-ups in about ten minutes. This guide shows how.

What you're looking for

The question isn't “is everyone busy?”. Everyone is busy. The question is “who has more things running at the same time than they can realistically move forward?”. That's about overlap, not hours.

Counting overlapping pieces of work per person is crude, but it's surprisingly good at finding the problems that matter. Someone with five projects open in the same month will be context-switching all day, and something will slip. You don't need precise effort estimates to see that.

Step 1: list the work with owners and dates

Start with every piece of work that's in flight or due to start in the next couple of months. For each one you need just three things:

  • Who owns it (one name, or the main names if it's shared).
  • When it starts.
  • When it's due.

Include the work that never makes it onto the roadmap: the migration someone is doing on the side, the recurring report, the support rota. Unlisted work is the most common reason a capacity check says “fine” when it isn't.

Step 2: pick a period and count overlaps

Split the next few months into equal periods. Weeks work for fast-moving teams; fortnights or months suit longer projects. Then, for each person and each period, count how many of their pieces of work are running at some point in it.

A simple grid does the job:

  • One row per person.
  • One column per period.
  • Each cell holds the number of their items that overlap that period.

In a spreadsheet, a COUNTIFS per cell will do it: count the rows where the owner matches, the start is before the period ends, and the due date is after the period starts.

Step 3: set a line and look for cells above it

Pick a number above which you'd expect trouble. For most people, three things running at once is about the most they can keep moving. Some roles, such as a lead who mainly reviews other people's work, can carry more. Others, like an engineer deep in a build, can carry fewer. Start with three and adjust once you've seen a few months of results.

Now scan for cells above the line. You're looking for two patterns:

  • Spikes. One person, one period, far too much. Usually several deadlines that happen to fall in the same month.
  • Plateaus. One person above the line for months on end. That's not a scheduling problem; it's a sign they own too much in general.

Step 4: fix the pile-ups while they're still cheap

A pile-up spotted two months out can usually be fixed by moving dates. A pile-up spotted in the week it happens can only be fixed by something slipping. For each problem cell, try these, roughly in this order:

  1. Stagger the starts. If two things don't need to run in parallel, start one after the other finishes. The total time is often similar, and both finish more reliably.
  2. Move a due date that nobody outside the team depends on. Internal dates are usually more flexible than they look.
  3. Hand something over. Is there someone below the line who could own one of the items?
  4. Drop or defer something. If none of the above works, the plan has more in it than the team can do. Better to decide what waits now than to find out by missing everything a little.

Step 5: repeat it monthly

Capacity changes every time a date moves. A one-off check goes stale within weeks. Make it part of a regular planning conversation; our guide to a monthly roadmap review has it as one of the standing items. Over time you'll also learn your own team's real line, which is more useful than any rule of thumb.

Where this simple check falls short

Counting overlaps is deliberately rough. Be aware of what it misses:

  • Size. A two-day task and a three-month project count the same. If your work varies a lot in size, give each item a rough weight (half, one, two) and add those up instead of counting.
  • Part-time and leave. Someone on leave for half of March has half the room. Lower their line for that period.
  • Shared ownership. If three people share an item, decide whether it counts fully for each of them or not at all, and be consistent.

None of that needs a specialist tool. It needs the check to happen regularly, with the real list of work, before the dates arrive.

Doing it in Plansies

Plansies has this check built in. In a work organisation, turn on Capacity in the board toolbar and you get a row per owner across the dates you're looking at, with the number of overlapping items in each period. Periods with more than three things at once are marked in red, and the busiest people are listed first. If your items have sizes, you can count those instead of one per item. Move a date and the counts follow it, so you can check that a fix actually clears the pile-up.